Calendar / How will the Futur Camp Nou be built?

Calendar / How will the Futur Camp Nou be built?

SUMMER 1:

• Demolition of the Lateral 1st Level
• Construction of the new Lateral 1st Level is completed
• Exterior construction at North and South Goals reaches Level 2
• Underground structure is built opposite the Grandstand area
• Ramps are modified, and Lateral pylons are installed
• Tunnels are prepared to protect the entrance and exit of spectators on match days

END SEASON 1:

• Main circulation areas North and South Goals are ready to be used.
• Spectators can sit in the new North and South Goals 3rd Level
• New video scoreboards are placed at the top of the new 3rd Level
• Exterior Grandstand and Lateral construction reaches Level 3 and spectators can safely circulate below
• New Lateral VIP Boxes can be used

 SUMMER 2:

• Demolition of the North Goal 1st Level
• Construction of the new North Goal 1st Level is completed
• Compression ring is put up for the roof above the Goals
• New seats are installed and exit corridors are widened
• Construction continues on outer rings of Grandstand and Lateral
• Field is renewed, if necessary
• Roof is torn down

END SEASON 2:

• Lateral and Grandstand 3rd Level is completed
• Compression ring is finished
• Preparation for the metal cable structure
• Beginning of construction of perimeter ring roofs
• New North Goal VIP Boxes can be used
• New Museum is completed opposite Grandstand area

SUMMER 3:

• New seats are installed and exit corridors are widened
• Metal cable roof structure is in position
• Maintenance footbridges for roof are installed
• New video scoreboards are moved to final position at the interior ends of the roof.
• Construction of perimeter ring roofs is continued
• New field put down

END SEASON 3:

• Interior work, bathrooms, and concessions are completed
• Elevators and escalators are installed in the main vertical circulation areas
• Installation of roof covering material is finished
• Construction of perimeter ring roofs ends
• New circulation rings and upper level VIP areas are finished

SUMMER 4:

• Demolition of South Goal and Grandstand 1st Level
• Construction of new South Goal and Grandstand 1st Level is completed

END SEASON 4:

• New bathrooms and concessions under South Goal and Grandstand 1st Level can be used
• New South Goal and Grandstand VIP Boxes can be used
• New Presidential Lounge can be used